Brompton Gasworks Community Update | June 2024
We are pleased to share the positive progress made since our last Community Update in May 2024. Our contractor, Enviropacific, has successfully completed the following project milestones:
- Four tarwells now completed with a further four in-ground structures (tarwells and fuel tanks) to be removed in the coming months.
- All tar containing structures to be remediated and removed by Q3, 2024.
- Ground water remediation commenced with data gap analysis and water treatment trials.
- Heavily impacted tar and tar fills continue to be removed from the site to a processing facility.
- Stephenson Environmental has recently concluded their odour analysis which has been issued to the independent auditor and the EPA for review.
- Enviropacific continue to work in collaboration with the independent auditor to seek opportunities to improve odour and air quality control and reporting.
MAB’s ongoing commitment is to provide timely updates as we progress towards transforming this site into a vibrant urban village that celebrates its historical identity.